photo 1

Footing along 10 line looking south where rain water has filled the footings.

photo 2

A continuous footing at the loading dock that is fully submerged by rain water.

photo 4

Finally some dry weather!  East wall at equipment room looking north after the rain water has been pumped out.

photo 5

Installation of the storm sewer inlet at the southwest corner of the equipment room.

photo 6

Installation of piers and stem wall at the equipment room is on-going.

photo 9

Electric service conduits installed as concrete workers continue to form and prep the south side of the Engine Room.