image 1

Looking North at the footing excavation along column line 10.

image 3

Looking East at the storm line south of the engine room being installed.

image 2

Looking North, workers prepare rebar for the footing at the dock office and loading dock.

image 6

Looking Southeast at the cleanout for the 6″ storm line.

image 4

Looking North, the continuous footing along column line 12 is ready to be poured.

image 8

And the rain begins!  Rain and high water table combine to make the site very saturated.

image 5

Footing K-10 is in the process of being poured.  This was one of the footings on K-line that had to be repaired due to the wood piles encountered.

image 9

Extremely heavy rains move in, leading to three days of weather delays.