Construction Progress Photos 07/27

Equipment being received at Port of Wilmington Cold Storage

Material Handling Equipment

Battery Chargers and charging stations.

The exterior of the office is looking good!

Tile in the restrooms and locker room areas.

Construction Progress photos 07/14

Ammonia arrives on site and is being loaded to the system.

Drop ceilings being installed in the office area.

More racks being installed!

Construction Progress Photos for 07/12

Concrete pours around the outside of the building.

Dock Doors installed.

Construction progress photos for 07/07

Installation of Racking in the freezer and Quick Freeze area continues.

Dock Plates being installed.

Ammonia Vessels

NC Ports!

The Port of Wilmington is Big Ship Ready!

Very interesting and exciting article!

goo.gl/ydgRG8