Footing along 10 line looking south where rain water has filled the footings.
A continuous footing at the loading dock that is fully submerged by rain water.
Finally some dry weather! East wall at equipment room looking north after the rain water has been pumped out.
Installation of the storm sewer inlet at the southwest corner of the equipment room.
Installation of piers and stem wall at the equipment room is on-going.
Electric service conduits installed as concrete workers continue to form and prep the south side of the Engine Room.