Installation of Racking in the freezer and Quick Freeze area continues.
Dock Plates being installed.
Ammonia Vessels
NC Ports!
Installation of Racking in the freezer and Quick Freeze area continues.
Dock Plates being installed.
Ammonia Vessels
NC Ports!
Very interesting and exciting article!
goo.gl/ydgRG8
Racks in the Blast area.
Racks in the Freezer.
Dock Plates being installed.
Exciting news for the Port of Wilmington! Please follow this link to read this article.
http://goo.gl/bZC9fQ
Pictures taken from the roof of the building
Rooftop view from our facility
Work continues on the interior floors of the warehouse
Set switchgear at the main electric room.
Began to install the exterior densglass at the office.
Began interior framing in the Engine Room.
Continue fine grading at the Cold Dock and the office.
Set the final vessel in the Engine Room.
Here is a recent article featuring our cold storage facility.
http://www.starnewsonline.com/article/20160326/NEWS/160329843/-1/archive?p=all&tc=pgall
Refrigeration piping progressing at cold dock roof.
Steel erection at the MHE room nearly complete.
Electrical equipment installation progressing at engine room.
Refrigeration equipment placed in the engine room.
Steel erection continues at the office and perimeter of the cold dock.
Primary power transformer set by Duke Energy.
Chuck Schoninger and Chuck McCarthy visit the construction site.
Successful slab pour in the electrical room.
Quick Freeze evaporator stands are installed at the penthouse.
Fine grading continues at the dock area.
Roof structure continues to be erected at the cold dock.
Recent Comments