image 09

View looking South of the East stem wall of the building.  Progress looks good!

image 08

Excavators working to chip out the existing storm line so that a new line can be installed.

image 07

Photo looking East down K Column line, footings have successfully been poured.

image 06

Photo of flowable fill over the transformer conduit at the engine room.